Alt Resources Ltd: Exploration Update Bottle Creek Gold Project

09.10.2018  |  ABN Newswire
Canberra, Australia - Alt Resources Ltd. (ASX:ARS) ("Alt or the Company") is pleased to provide the following information on exploration progress at the Bottle Creek Gold Project. Challenge Drilling has completed an 3000 metres of the planned 5000 metre Phase 3 RC drilling program at the Company's flagship Bottle Creek Gold Project with all sampling from the RC program delivered to ALS laboratories in Kalgoorlie. Assayed results will be announced to the market over the coming weeks.

Highlights

- 3000 metres Phase 3 RC drilling program now completed at Bottle Creek

- Additional 2000 metres to be drilled in October

- All sampling delivered to ALS Kalgoorlie lab with assays expected in coming weeks

- All conditions now satisfied to complete "Option to Purchase Agreement" Bottle Creek Gold Project

- Favourable settlement terms for payment of the Bottle Creek Gold Project negotiated with the Vendor and announced (see Note below)

- First resource upgrade on schedule for delivery in October 2018

Challenge will be drilling a further 2000 metres of RC to complete the planned 5000 metres of Phase 3 drilling by end of October. Phase 3 is testing directly north of the mined VB pit, an unmined section of the project between the VB and Boags pits and directly south of the unmined Southwark deposit (see Figure 2 in link below). All Phase 3 drilling is designed to bring additional resource ounces into the resource table quickly with the Company twinning designated holes validating historical drilling and adding additional drill fences as infill.

The Company is fast tracking resource drilling and historical drill hole validation at the Bottle Creek Gold Project to bring the resource as quickly as possible towards a critical mass for mine planning and a feasibility study. Resource upgrades will be announced sequentially as Phase 2 and Phase 3 results are input and modelled by resource geologists. We expect to announce Phase 2 resource upgrade in October with the 3rd Phase resource upgrade to be announced by the end of the 2018.

The Company considers Bottle Creek to have the potential to underpin a stand-alone processing plant in the northern end of the Mt Ida gold belt with significant sunk capital in the project by the previous miner Norgold with Figure 3 (see link below) showing the VB and Boags pits, the Bottle Creek airstrip, tailings dams and the pre stripped Emu deposit as indicative of some of the existing infrastructure expenditure and sunk capital in the project.

Alt is actively pursuing other opportunities in the Mt Ida region including acquiring assets close to the Bottle Creek mining leases which may be considered stranded assets by other exploration and mining companies.

Note: http://www.abnnewswire.net/press/en/94730/

To view figures, please visit:
http://abnnewswire.net/lnk/8X4WH2K8



About Alt Resources Ltd:

Alt Resources Ltd. (ASX:ARS) is an Australian based mineral exploration company that aims to become a gold producer by exploiting historical and new gold prospects across quality assets and to build value for shareholders. The Company's portfolio of assets includes the newly acquired Bottle Creek gold mine located in the Mt Ida gold belt, the Paupong IRG Au-Cu-Ag mineral system in the Lachlan Orogen NSW, Myalla polymetallic Au-Cu-Zn project east of Dalgety in NSW and the Mt Roberts gold project located near the town of Leinster in WA.

Alt Resources, having acquired historical and under-explored tenements in the Mt Ida Gold Belt, aims to consolidate the historical resources, mines and new gold targets identified within the region. Potential at Mt Ida exists for a centralised production facility to service multiple mines and to grow the Mt Ida Gold Belt project to be a sustainable and profitable mining operation.



Source:

Alt Resources Ltd.



Contact:

James Anderson CEO Alt Resources Ltd. E: james.anderson@altresources.com.au Peter Taylor Investor Relations E: Peter@nwrcommunications.com.au M: +61-412-036-231


Bewerten 
A A A
PDF Versenden Drucken

Für den Inhalt des Beitrages ist allein der Autor verantwortlich bzw. die aufgeführte Quelle. Bild- oder Filmrechte liegen beim Autor/Quelle bzw. bei der vom ihm benannten Quelle. Bei Übersetzungen können Fehler nicht ausgeschlossen werden. Der vertretene Standpunkt eines Autors spiegelt generell nicht die Meinung des Webseiten-Betreibers wieder. Mittels der Veröffentlichung will dieser lediglich ein pluralistisches Meinungsbild darstellen. Direkte oder indirekte Aussagen in einem Beitrag stellen keinerlei Aufforderung zum Kauf-/Verkauf von Wertpapieren dar. Wir wehren uns gegen jede Form von Hass, Diskriminierung und Verletzung der Menschenwürde. Beachten Sie bitte auch unsere AGB/Disclaimer!



Mineninfo
Alt Resources Ltd.
Bergbau
A14L8K
AU000000ARS9

Copyright © Minenportal.de 2006-2024 | MinenPortal.de ist eine Marke von GoldSeiten.de und Mitglied der GoldSeiten Mediengruppe
Alle Angaben ohne Gewähr! Es wird keinerlei Haftung für die Richtigkeit der Angaben und der Kurse übernommen!
Informationen zur Zeitverzögerung der Kursdaten und Börsenbedingungen. Kursdaten: Data Supplied by BSB-Software.