Minera Alamos Releases Operations Update and Q3 Financials

30.11.2023  |  Newsfile

Toronto, November 30, 2023 - Minera Alamos Inc. (TSXV: MAI) (the "Company" or "Minera Alamos") is pleased to provide an operations update and select financial highlights from the third quarter of 2023 as well as some highlights of corporate activities during the quarter and the year. For a full overview please refer to the Q3 Financial Statements and MD&A filed on Sedarplus.ca on November 29th, 2023.

Highlights

Operational Updates

Following a scale-up in the resources (equipment/workforce) from the Company's mining contractor, production rates at the Santana project increased in Q3 and averaged over 70,000 tonnes of total material (mineral + waste) moved per month which was in line with plans.

The Company continues to have constructive communications with SEMARNAT regarding the delayed permit amendment application which will triple the overall leach pad capacity at Santana and provide the necessary capacity for full Nicho Main Zone development. All requested follow-up technical information has been submitted by the Company as part of that dialogue and no additional requests were received in the quarter. Plans continue to advance with the Company's contractor to finalize required construction details related to the leach pad expansion outlined in the permit applications.

Exploration drilling at the Santana project is ongoing at the Benjamin target area and the release of drilling results are pending. Following the completion and analysis of the current round of data from the Benjamin and Zata prospects the Company will be preparing plans for its 2024 exploration activities. Also included for these upcoming plans will be additional drill programs to further delineate the known gold resources at the Cerro de Oro project as well as zones for resource expansion. The Company remained active in the Cerro de Oro area throughout the quarter with mapping and targeting activities covering the large concession package surrounding the currently defined resources.

Work activities related to the Cerro de Oro project will continue to expand through Q4 and into 2024 following the completion of the Auramet financing facility for the project's development. This will include:

Selected Financial Data

The following selected financial data is summarized from the Company's Financial Statements and related notes thereto (the "Financial Statements') for the quarter ended September 30th, 2023, and the Management's Discussion and Analysis ("MD&A") for the quarter ended September 30th, 2023 (all numbers in Canadian dollars unless otherwise stated). A copy of the Financial Statements and MD&A is available on SEDARplus at www.sedarplus.ca.

Cautionary Statement

The Company made its production decision at the Santana gold mine without having completed a feasibility study demonstrating economic and technical viability. As such, there may be increased uncertainty of achieving planned production levels, estimated recovery of gold, the costs associated with such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure.

Mr. Darren Koningen, P. Eng., Minera Alamos' CEO, is the Qualified Person responsible for the technical content of this press release under National Instrument 43-101.

For Further Information Please Contact:

Minera Alamos Inc.
Doug Ramshaw, President
Tel: 604-600-4423
Email: dramshaw@mineraalamos.com
Website: www.mineraalamos.com

Victoria Vargas de Szarzynski, VP Investor Relations
Tel: 289-242-3599
Email: vvargas@mineraalamos.com

About Minera Alamos Inc.

Minera Alamos is a gold production and development Company undergoing the operational start-up of its first gold mine that produced its first gold in October 2021. The Company has a portfolio of high-quality Mexican assets, including the 100%-owned Santana open-pit, heap-leach mine in Sonora that is currently going through its operational ramp up. The 100%-owned Cerro de Oro oxide gold project in northern Zacatecas has considerable past drilling and metallurgical work completed and the proposed mining project is currently undergoing permitting. The La Fortuna open pit gold project in Durango (100%-owned) has a positive, robust preliminary economic assessment (PEA) completed, and the main Federal permits are in place. Minera Alamos is built around its operating team that together brought three open pit heap leach gold mines into successful production in Mexico over the last 13 years.

The Company's strategy is to develop very low capex assets while expanding the projects' resources and continuing to pursue complementary strategic acquisitions.

Caution Regarding Forward-Looking Statements

This news release may contain forward-looking information and Minera Alamos cautions readers that forward-looking information is based on certain assumptions and risk factors that could cause actual results to differ materially from the expectations of Minera Alamos included in this news release. This news release includes certain "forward-looking statements", which often, but not always, can be identified by the use of words such as "believes", "anticipates", "expects", "estimates", "may", "could", "would", "will", or "plan". These statements are based on information currently available to Minera Alamos and Minera Alamos provides no assurance that actual results will meet management's expectations. Forward-looking statements include timing, cost estimates and statements with respect to Minera Alamos' future plans, objectives and goals with respect to the Cerro de Oro gold mine including the receipt of permits and construction timeline, and the satisfaction by the Company of the closing conditions to draw the Remaining Amount. Since forward-looking statements are based on assumptions and address future events and conditions that, by their very nature involve inherent risks and uncertainties. Actual results relating to, among other things, results of exploration, the economics of processing methods, project development, reclamation and capital costs of Minera Alamos' mineral properties, the ability to complete a preliminary economic assessment which supports the technical and economic viability of mineral production could differ materially from those currently anticipated in such statements for many reasons. Minera Alamos' financial condition and prospects could differ materially from those currently anticipated in such statements for many reasons such as: an inability to finance and/or complete an updated resource and reserve estimate and a preliminary economic assessment which supports the technical and economic viability of mineral production; changes in general economic conditions and conditions in the financial markets; changes in demand and prices for minerals; litigation, legislative, environmental and other judicial, regulatory, political and competitive developments; technological and operational difficulties encountered in connection with Minera Alamos' activities; and other matters discussed in this news release and in filings made with securities regulators. This list is not exhaustive of the factors that may affect any of Minera Alamos' forward-looking statements. These and other factors should be considered carefully, and readers should not place undue reliance on Minera Alamos' forward-looking statements. Minera Alamos does not undertake to update any forward-looking statement that may be made from time to time by Minera Alamos or on its behalf, except in accordance with applicable securities laws.

The Company does not have a feasibility study of mineral reserves, demonstrating economic and technical viability for the Santana project, and, as a result, there may be an increased uncertainty of achieving any particular level of recovery of minerals or the cost of such recovery, including increased risks associated with developing a commercially mineable deposit. Historically, such projects have a much higher risk of economic and technical failure.

NEITHER TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/189255