Artemis Gold provides an update on Q4 construction progress at the Blackwater Minea. The project remains fully funded, within the guidance for initial capital expenditure, and on schedule for first gold pour in H2 2024. At December 31, 2023, overall construction was 59% complete, and approximately C$389 million of the guided initial capital expenditure of C$730 to C$750 million had been spent. The lag between the spend
[...]