Anooraq Resources Corporation Provides an Operational Update for Bokoni Mines
- Production volumes increasing
- Unit costs continuing to decrease
- Implementation of concentrator plant upgrade
VANCOUVER, June 21 /CNW/ - Anooraq Resources Corporation ("Anooraq" or the "Company") (TSXV: ARQ; NYSE Amex: ANO; JSE: ARQ) is pleased to provide an update on operational progress at its flagship operation, Bokoni Platinum Mines ("Bokoni"), during the second quarter of the current financial year ("Q2 2010").
Further to finalization of a significant labour restructure at Bokoni during the first quarter of the current financial year ("Q1 2010"), Q2 2010 has seen the successful implementation of the Bokoni labour restructure, resulting in increased production volume and decreased unit costs at the operations.
Increase in stoping activities
The labour restructure focused primarily on improving the balance at Bokoni to ensure that more employees were placed in revenue-generating activities, as opposed to mine support services. This resulted in 11 new stoping teams being introduced to the operations, with total stoping teams increasing from 70 to 81 during the quarter. It is anticipated that a total of 100 stoping teams will be active at Bokoni by the end of the fourth quarter of the 2010 financial year ("Q4 2010").
Production volumes increasing
As anticipated, production volumes are beginning to increase, with a steady upward trend in month-on-month production from April 2010 onwards. Subsequent to the labour restructure, vamping operations have also commenced at Bokoni and production from vamping activities should increase to approximately 6,000 tonnes per month ("tpm") by December 2010.
The Company anticipates an increase in Q2 2010 production growth of not less than 15% when compared with Q1 2010.
Brakfontein Merensky Project
Production at the new Brakfontein Merensky shaft has started to increase and it is anticipated that production volumes from this shaft will increase by 100% from its Q1 2010 production base to 30,000 tpm by the end of Q4 2010. At steady state production, the Brakfontein operation will produce at 120,000 tpm.
Unit costs decreasing
As a result of improving production at the operations and continued stringent cost controls, operational unit costs continue to decrease and management is confident that the Company will meet its first cost-cutting target of ZAR 905 per tonne milled (USD 120 per tonne milled) by June 2010, as previously stated.
Implementation of concentrator plant upgrade
The recently announced Bokoni concentrator plant upgrade project was implemented during Q2 2010. The project encountered some challenges, which resulted in greater than anticipated mill stops as well as lower recoveries than planned. These issues had a negative impact on the operations during the beginning of Q2 2010, but all teething problems have been addressed and the concentrator has returned to meet design parameter targets with respect to recoveries and throughput.
During this period there was also a change in the management team at the Bokoni concentrator. The team is now lead by Mr. Attie de Lange, who joined Bokoni from Anglo Platinum Limited's Mogalakwena section where he previously was concentrator manager for four years.
Release of full financial statements
The Company plans to release full financial statements for the three and six months ended June 30, 2010 during August 2010.
Philip Kotze, the Chief Executive Officer of Anooraq, said, "We are pleased that the benefits of the labour restructure are starting to demonstrate positive results at the operations, both in volume growth and unit cost reductions. I am also encouraged by our new management team's approach at the concentrator during commissioning of the upgrade project. Our next challenge will be to continue to demonstrate a positive trend line on volume increases and unit cost reductions as we move into the second half of the year. I am confident that we have laid the correct foundation for our future expansion plans and that we have the right management team in place to achieve these objectives."
For further information, please visit our website www.anooraqresources.com, call investor services in South Africa at +27 11 883 0831 or in North America at 1 800 667 2114 or use the contacts referenced below.
The TSX Venture Exchange does not accept responsibility for the adequacy or accuracy of this release.
The NYSE Amex has neither approved nor disapproved the contents of this release.
Cautionary and Forward Looking Information
This document contains "forward-looking statements" that were based on Anooraq's expectations, estimates and projections as of the dates as of which those statements were made. Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as "outlook", "anticipate", "project", "target", "believe", "estimate", "expect", "intend", "should" and similar expressions.
Forward-looking statements are subject to known and unknown risks, uncertainties and other factors that may cause the Company's actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking statements. These include but are not limited to:
- uncertainties and costs related to the Company's exploration and
development activities, such as those associated with determining
whether mineral resources or reserves exist on a property;
- uncertainties related to feasibility studies that provide estimates of
expected or anticipated costs, expenditures and economic returns from
a mining project; uncertainties related to expected production rates,
timing of production and the cash and total costs of production and
milling;
- uncertainties related to the ability to obtain necessary licenses,
permits, electricity, surface rights and title for development
projects;
- operating and technical difficulties in connection with mining
development activities;
- uncertainties related to the accuracy of our mineral reserve and
mineral resource estimates and our estimates of future production and
future cash and total costs of production, and the geotechnical or
hydrogeological nature of ore deposits, and diminishing quantities or
grades of mineral reserves;
- uncertainties related to unexpected judicial or regulatory
proceedings;
- changes in, and the effects of, the laws, regulations and government
policies affecting our mining operations, particularly laws,
regulations and policies relating to
- mine expansions, environmental protection and associated
compliance costs arising from exploration, mine development, mine
operations and mine closures;
- expected effective future tax rates in jurisdictions in which our
operations are located;
- the protection of the health and safety of mine workers; and
- mineral rights ownership in countries where our mineral deposits
are located, including the effect of the Mineral and Petroleum
Resources Development Act (South Africa);
- changes in general economic conditions, the financial markets and in
the demand and market price for gold, copper and other minerals and
commodities, such as diesel fuel, coal, petroleum coke, steel,
concrete, electricity and other forms of energy, mining equipment, and
fluctuations in exchange rates, particularly with respect to the value
of the U.S. dollar, Canadian dollar and South African rand;
- unusual or unexpected formation, cave-ins, flooding, pressures, and
precious metals losses (and the risk of inadequate insurance or
inability to obtain insurance to cover these risks);
- changes in accounting policies and methods we use to report our
financial condition, including uncertainties associated with critical
accounting assumptions and estimates;
- environmental issues and liabilities associated with mining including
processing and stock piling ore;
- geopolitical uncertainty and political and economic instability in
countries which we operate; and
- labour strikes, work stoppages, or other interruptions to, or
difficulties in, the employment of labour in markets in which we
operate mines, or environmental hazards, industrial accidents or other
events or occurrences, including third party interference that
interrupt the production of minerals in our mines.
For further information on Anooraq, investors should review the Company's annual Form 20-F filing with the United States Securities and Exchange Commission www.sec.com and home jurisdiction filings that are available at www.sedar.com.
For further information:
Queries: Joel Kesler, Executive: Corporate and Business Development
Office: +27 11 779 6800, Mobile: +27 82 454 5556
Russell and Associates
Charmane Russell, Nicola Taylor
Office: +27 11 880 3924, Mobile: +27 82 372 5816, +27 82 927 8957
Macquarie First South Advisers
Melanie de Nysschen
Office: +27 11 583 2000, Mobile: +27 82 465 8969